CA03 - Display Routing

The standard values Based Quantity = (Direct labour hours + Setup tools + Machining times + Adjust/Service Tools)
e.g.  Operation :-     100                  =             1                 +       1           +           1             +            1

This means that to produce 100 pieces, you need a total activities of 4 hrs.