Planned Independant Requirement included/excluded in MRP run

MD62 - Look for the indicator version

Tick    to include in MRP run
Untick to exclude in MRP run

OMPG - Define consumption mode and period of adjustment.
MM02 - The field in Material Master (MRP Group) determine whether the configuration is check during MRP run.

For example, if you configure consume forward as 2 days.  During MRP run, forcast (VSF) must be at least 2 days ahead of the last firm Sales Order or it would be consume into the Sales Order.