Question : Subject : PS Network Status's & Confirmations

Sappers:

Is there a status that can be set for a network activity that will stop time confirmations from being processed? TECO stops changes to the basic data, but allows further time confirmations.

TIA
 

Reply : Subject : PS Network Status's & Confirmations

hi...

you can lock account assignment for the network/activity in consideration depending on whether the network is header/activity
assigned. This disallows the confirmation of the activities.

...else you can use the user status

regards...