We have a problem with mrp.
I get lots of purchase requests on a daily basis & after a lot of effort, they now mostly reflect appropriate quantities of materials to buy. The problem is timing. A typical scenario is the day after I've placed an order on a vendor, there will be a request to purchase another product from the same vendor. Typically we will have sold justone more unit, bringing stock levels down to the reorder point, hence the request.
Given that usually that the additional sale was within the forecast
level for the month, what do i need to do to get mrp to produce requests
for all the vendors materials that will need to be ordered before the end
of the month? Not only is this starting to drive me up the wall, my suppliers
are starting to express frustration as well
Answer : Subject: MRP, timing of purchase requests
Hi,
I feel u can change the planning from Reorder point based to regular
planning. Also, u can set up the Delivery schedules with Firming
zone and TRade off zones.So, When the higher level assembly is planned
based on some forecast, it will explode the BOM and dependent requirements
are generated for the entire planning horizon.Based on the settings, delivery
schedules within Firming period gets firmed and u can transmit it to ur
Suppliers and also transmit the future/forecast schedules also for ur Vendor's
knowledge and info.He will be prepared for the next set of requirements.Even
if material is stock, according to forecast, some delivery schedules in
TRade off zone (not firmed) will be generated and ur supplier can be prepared.
Alos, try to match the frequency of MRP run with ur requirement of
passing the info. to ur suppliers.
Hope this change in the business process will help.
Answer : Subject: MRP, timing of purchase requests
I agree with mvm. If you are going to the trouble of putting together a sales forecast, why are you using reorder point planning? Let the forecast trickle down through all levels of the BOM and use it to drive procurement (either internal or external) of your lower level components. I assume that the forecast is being entered into SAP, probably in S&OP. If not, you have a bigger issue on your hands.